SG Elite was commissioned by Aggregate Industries to deliver enabling works at Bardon Hill Quarry, supporting the installation of an 800m suspended conveyor. This new system was key to expanding the quarry’s capacity and efficiency.
Working in challenging conditions—on 33-degree slopes, in winter weather, and amid tough rock formations—our team provided rock anchor installations, earthworks, ground clearance, and rock breakout. All work was carried out in a live quarry with minimal disruption to operations.
Two Menzi M545s and a Menzi M540, tethered for safety, tackled the steep terrain with support from a restraint excavator and secondary safety systems. Using rock saws and Epiroc MB1200 hydraulic breakers, we excavated 3,500m³ of rock at both conveyor endpoints.
To ensure safety on high-risk terrain, we collaborated with a leading IRATA rope access team. Our operators worked 24/7 over four months of active construction to meet strict deadlines and operational requirements.
Through expert planning, slope stability assessments, and compliance with quarry legislation, SG Elite delivered a high-impact solution. The project’s success enabled the conveyor installation and future-proofed Aggregate Industries’ operations—on time, within budget, and without compromising safety or quality.