SG Elite delivered a vital drainage project at the Dinmore Tunnel North Portal, installing 30 counterfort drains—each 24m long—on steep 45-degree cuttings above the live Welsh Marches line. The works were essential in preventing slope failure and ensuring continued rail safety.
Working within our Any Line Open (ALO) Safe System of Work, we operated safely above an active railway without requiring possession periods—drastically reducing project time and cost. Two teams worked simultaneously on either side of the track, installing 15 counterforts per side to accelerate delivery.
Overcoming saturated and hard ground, our team used specialist excavation techniques to achieve precise installation depths and widths in line with engineering specifications. We provided rock breaking where required and supported the Temporary Works Designer (TWD) with slope stability assessments and tethering solutions.
Environmental impact was carefully managed, with reduced muck-away and backfill needs, and daily ecological measures coordinated with the client.
Delivered in close partnership with AMCO Giffen, TRS, and Network Rail, the project stabilised the cutting and protected a critical rail corridor. SG Elite’s commitment to safety, sustainability, and innovation ensured a successful outcome under complex conditions—without interrupting passenger services.