Umbourne Cutting Retention and Drainage

Rail

M545, M220

Axminster, England

SG Elite successfully delivered a complex infrastructure project at Umbourne Cutting, installing over 120 metres of King Post Walls and Counterfort Drainage to resolve severe slope failure and drainage issues.

With no land access above the cutting, we implemented a restricted access solution and worked within our Any Line Open (ALO) Safe System of Work—maintaining continuous rail operations without requiring costly possession periods.

Challenging ground conditions, including hard excavation and a failed 32-degree slope, demanded both precision and innovation. We alternated between augering and vibro hammer methods to suit the varying strata, while our bespoke anchor system stabilised Menzi equipment during works on the steep incline.

Using a tandem of Menzi M220 and M545 excavators enabled us to operate with agility and control across the demanding terrain. This approach, combined with close collaboration with Balfour Beatty and Network Rail, ensured safe, efficient delivery with major time, cost, and carbon savings.

The result: a safer, more resilient rail corridor along the Welsh Marches line—completed without disrupting services. SG Elite’s commitment to smart engineering and sustainable solutions once again proved key in protecting vital transport infrastructure.