Skip to Content

Hammer Embankment
Retention & Drainage

Rail

M540, M545

Haslemere, England

SG Elite successfully completed a complex project at Hammer Embankment, stabilising a steep slope between a live railway and a river. The works involved installing a retention wall, over 80 soil nails, and advanced drainage systems—resolving critical drainage issues and preventing slope failure.

Using our Any Line Open (ALO) Safe System of Work, we carried out operations adjacent to the live Welsh Marches line without the need for full possession, drastically reducing project time and cost.
The site presented numerous challenges, including saturated ground, a 30-degree slope, and limited access. We developed a restricted access strategy, with materials delivered across the river and work undertaken during minimal possession windows.

Our expert team used a combination of drilling, hammering, and excavation techniques to adapt to ground conditions while optimising speed and safety. We also regraded the embankment and worked with the client to create efficient methodologies that reduced carbon output and environmental impact.

Delivered in collaboration with Balfour Beatty and Network Rail, the project ensured the long-term safety of this vital transport link. SG Elite’s innovative, safety-first approach once again delivered measurable value through engineering excellence and sustainable project execution.