Skip to Content

Restricted Access
Rocksaw

Rail

M540, M545

Stalybridge, England

Our highly skilled operators played a key role in a critical project at Stalybridge, providing efficient and safe concrete slab removal to facilitate track realignment. Working alongside BAM, our team utilised the walking excavator paired with a rocksaw, featuring a 1600mm loop cutting blade, to swiftly and precisely remove the existing concrete slab.

The primary objective of this operation was to realign the track to accommodate a newly installed platform. The track needed to be moved approximately 200-300mm to match the profile of the platform, and our approach was designed to optimise both time and safety. By using the walking excavator and Rocksaw, we significantly reduced setup times compared to traditional methods,

Our operator navigated range of obstacles enroute to the works face, completing a precise 35-meter cut following the curvature of the platform at a depth of approximately 450-500mm. This efficient solution reduced the number of personnel required, ensuring a smoother, safer operation and minimising disruption to overall programme.

Default Graphic (Left) for SG Elite Default Graphic (Right) for SG Elite

Services Used

Trained For All Terrains

Contact Us